PIDP Award Analytics — FY2019 → FY2025

Port Infrastructure Development Program • U.S. Maritime Administration (MARAD) • Every round analyzed on the FY2025 template, with program-to-date roll-ups
Awarded
$774.1M
▲ 34.2% vs prev
Awards
37
▲ 19.4% vs prev
Applications
186
▲ 17.7% vs prev
Success Rate
19.9%
prev 19.6%
Oversubscription
3.96×
req ÷ awarded

Program Trend — FY2019 to FY2025

Full program history. The selected year is highlighted. Toggle the metric.
Awarded $
Applications
Awards
Requested $
Success Rate
Oversubscription

Cumulative Roll-Up — Program to Date

Running totals through each fiscal year (the roll-up of all prior rounds). Bars = annual; line = cumulative.
Awarded $
Awards
Applications

Awards by State — FY25 SINGLE YEAR

Toggle metric. Top 15 states shown.
Awarded $
Applications
Awards
Capture Rate

Project Category

Construction / Planning / Both (by $ awarded).

Special Categories

Inland, Energy, Rail, Tribal & more.

Leverage → Win Rate

Non-federal cost share band vs success rate.

Award Detail — FY25 SINGLE YEAR

37 awardsTotal: $774.1M
YrStateApplicantProjectCategoryProject CostRequestAwardLeverageTags
FY25GUPort Authority of GuamStrengthening Supply Chain with New Port CranesConstruction$74.6M$59.7M$59.7M20%
FY25GAGeorgia Ports AuthorityLay Berth and Supply Chain Optimization ProjectBoth$162.0M$53.0M$53.0M67%
FY25TXPort HoustonStrategic Terminal Operations and Resilience MeasuresConstruction$104.2M$48.0M$48.0M54%
FY25LAPort of South LouisianaDonaldsonville Dock Conveyance SystemBoth$256.5M$48.9M$43.4M81%Inland Energy
FY25MDMaryland Economic Development CorporationTradepoint Atlantic TiL Terminal - Phase 2 FY25Construction$77.4M$39.7M$39.7M49%
FY25AKMunicipality of SkagwayPort of Skagway Industrial Dock Redevelopment ProjectBoth$51.5M$38.6M$38.6M25%Energy
FY25TXPort of Beaumont Navigation District of Jefferson County, TXPort of Beaumont Rail Enhancement ProjectConstruction$47.2M$37.8M$37.8M20%Rail
FY25AKState of Alaska Department of TransportationPort Mackenzie Multimodal Port ExpansionConstruction$72.0M$34.0M$34.0M53%Rail
FY25MPCommonwealth Ports AuthorityDelta Dock Rehabilitation ProjectConstruction$30.5M$30.5M$30.5M0%
FY25MNDuluth Seaway Port AuthorityMultimodal Terminal ExpansionConstruction$38.4M$27.5M$27.5M28%
FY25MOMarion Ralls County Regional Port AuthorityWest Quincy Port Development ProjectConstruction$39.4M$27.3M$27.3M31%Inland
FY25FLPort Tampa BayRedwing Berth 300 ExtensionConstruction$40.0M$24.0M$24.0M40%
FY25WVWest Virginia Department of TransportationNucor Steel West Virginia – Material Handling TerminalConstruction$52.2M$23.5M$23.5M55%Inland Energy
FY25AKAlaska Railroad CorporationARRC Port of Whittier Operational Efficiency ProjectConstruction$29.0M$20.4M$20.4M30%Rail
FY25FLCanaveral Port AuthorityPort Canaveral North Cargo Berths 1 and 2 Rehabilitation ProjectConstruction$37.4M$20.2M$20.2M46%
FY25WICity of ManitowocMidwest Multi-Modal Development ProjectConstruction$38.3M$20.0M$20.0M48%Inland
FY25TNMidSouth Development DistrictInternational Port of Memphis Cement and SCM Distribution Terminal and CNG StationConstruction$39.3M$19.7M$19.7M50%Inland Energy
FY25VAPortsmouth Port and Industrial CommissionPortsmouth Agricultural Intermodal Export Facility - Phase 2Construction$22.9M$16.4M$16.4M28%
FY25MIPort of MonroeCargo Resiliency and Manufacturing Infrastructure ProjectConstruction$18.8M$15.0M$15.0M20%Inland Energy
FY25PRPuerto Rico Industrial Development CompanyEnergy and Logistics Hubs ProjectsBoth$61.2M$11.9M$11.9M80%Energy
FY25CACity of MontereyStrengthening Monterey Wharf II - Seismic Upgrades and Rehabilitation Project for Fisheries and BeyondConstruction$14.1M$11.3M$11.3M20%
FY25MICity of HollandHolland Intermodal Port ImprovementsConstruction$19.3M$11.3M$11.3M42%
FY25MSMississippi State Port AuthorityGulfport Intermodal Improvement ProjectConstruction$24.6M$11.3M$11.3M54%Rail
FY25OROregon International Port of Coos BayPacific Coast Intermodal Port (PCIP) Terminal Connection ProjectConstruction$68.7M$11.3M$11.3M84%Rail
FY25RIQuonset Development CorporationPort Readiness ImprovementsConstruction$24.0M$11.3M$11.3M53%
FY25WAPort of EverettPier 3 ModernizationConstruction$14.1M$11.3M$11.3M20%
FY25ILKaskaskia Regional Port DistrictNew South Dock for Improved Safety, Reliability, and Increased Cargo StorageConstruction$16.2M$11.2M$11.2M31%Inland Rail
FY25AKCity of HomerHomer Port Coastal Freight ProjectBoth$17.1M$11.2M$11.2M34%
FY25CAPort of RichmondDock Restoration for Improved Vehicle Entry (DRIVE)Construction$14.0M$11.2M$11.2M20%
FY25ILSeneca Regional Port DistrictEnhancing and Expanding the Economic Capacity and Output on the Illinois RiverConstruction$17.9M$11.2M$11.2M37%Inland Rail
FY25FLCity of JacksonvilleMayport Dock Redevelopment - Phase IIConstruction$14.0M$11.2M$11.2M20%
FY25TXPort FreeportVelasco Terminal ImprovementConstruction$22.0M$16.5M$11.0M25%
FY25WASwinomish Indian Tribal CommunityPort of Swinomish Infrastructure ModernizationConstruction$10.8M$10.8M$10.8M0%Tribal
FY25ALCity of ChickasawPort of Chickasaw Rehabilitation ProjectConstruction$17.2M$11.3M$7.0M34%
FY25AKMunicipality of Anchorage - Port of AlaskaPetroleum Terminal Replacement Planning ProjectPlanning$8.2M$4.7M$4.7M42%Energy
FY25AKThe City of WhittierPlanning and Design of the Delong Dock Replacement ProjectPlanning$5.1M$4.1M$4.1M20%
FY25AKCity of ChevakCev’aq River Marine Barge Landing FacilityPlanning$2.4M$2.4M$2.4M0%Tribal

Frequently asked questions

What is the Port Infrastructure Development Program (PIDP)?
PIDP is the U.S. Maritime Administration (MARAD) grant program that funds coastal, inland, and Great Lakes port infrastructure to improve capacity, efficiency, resilience, and the movement of freight through American ports.
What does the PIDP Award Analytics dashboard show?
It analyzes seven years (FY2019–FY2025) of MARAD PIDP awards — funding trends over time, applicant success rates, state-by-state breakdowns, project categories, and a leverage-to-win analysis of how cost-share ratios relate to award outcomes.
What is leverage-to-win analysis?
It examines the relationship between the non-federal cost share an applicant commits (its leverage) and the likelihood of winning a PIDP award, helping port sponsors benchmark competitive match levels.
Where does the PIDP data come from?
From MARAD's published PIDP award announcements for fiscal years 2019 through 2025, compiled and normalized by Prosody Labs.